Tel: 0845 036 2000
Fax: 01709 369 948
Email: info@megalift.uk.com
The MEGALIFT team was called upon to use its flair
and creativity to devise a solution for a problem involving a tanker
of dangerous chemicals. The tanker, which had become bonded to its
trailer, needed to be moved to a safe place for disposal.
The chemicals were extremely flammable, and as such the whole
building had to be cocooned to create a safety bubble. This created
difficulties in lifting the vessel. Health and safety officers in
charge of the area would not sanction the removal of any of the
protective cocoon during the lifting of the vessel; this greatly
reduced the options open the engineers.
The MEGALFT team was brought in to assist with the safe removal of
the vessel and initially carried an engineering study and risk
assessment. From this they created a novel solution to the problem.
The MEGALIFT tracks were laid, travelling from outside the
protective sheeting through and up to the vessel. The MEGALIFT
jacking legs were erected on the tracks outside the protective
sheeting. 12 metre lifting beams were fitted to the MEGALIFT system
creating two long arms with which to lift the vessel. To counter
balance the weight of the vessel during lifting, 20t of ballast was
attached to the rear of the system.
It was agreed that the vessel needed to be lifted at several points
while monitoring the load, to ensure the integrity of the vessel and
the safe handling of the chemicals. Several slings were therefore
passed around the body of the vessel. At each lifting point a Load
Shackle was attached enabling the loading to be monitored
accurately.
The MEGALIFT system was moved along its tracking until the slings
could be attached to the lifting beams by means of lever hoists. The
vessel was then removed from the building by reversing the MEGALIFT
system along its tracks. Plastic sheeting was placed over the vessel
as it emerged to protect it from the elements.
Everyone was extremely pleased that the potentially dangerous vessel
had been removed safely thanks to the care and creativity applied by
the MEGALIFT team.